Nice to be piling in a scenic location with glorious views!
Despite wet chalky ground conditions, we were able to make this project look quite neat by the time we finished.
First installing 16x 300mm dia CFA piles with our restricted access T15 piling rig, and then installing the 70 metres of 450 x 450mm reinforced concrete ground beams.
All in all, another tidy job!