Restricted Access? No Problem!

Due to complications with existing drainage, 4 No. Auger bored piles were the answer to enable this rear extension to be built.

Even with our small T15000 rig, access was incredibly tight so a crane was required to get the rig in and out.

All in a days work.

Spec sheets for all our rigs including the T15000 can be found here.